Jet-Grouting.com: A technical resource for Jet Grouting, Ground Modification, Ground Improvement
jet-groutings
JET GROUTINGS TECHNOLOGY OVERVIEW
JET GROUTINGS SPECIFICATIONS
JET GROUTINGS TECHNICAL ARTICES
JET GROUTINGS CASE HISTORIES
JET GROUTINGS INDUSTRY DIRECTORY
JET GROUTINGS EVENT CALENDAR
JET GROUTINGS JOBS
JET GROUTINGS DISCUSSION FORUMS
JET GROUTINGS ENGINEERS ESTIMATES
JET GROUTINGS TECHNICAL ASSITANCE
CONTACT JET-GROUTINGS.COM
RETURN TO JET-GROUTINGS.COM
JET GROUTINGS



Jet-Grouting.com: A technical resource for Jet Grouting, Ground Modification, Ground Improvement
Print This Page!
JET GROUTING
CASE HISTORIES

OUTER HARBOR
Buffalo, New York

Remedial Construction Services, L.P. (RECON) was contracted by Honeywell International to use its soil mixing and jet grouting technologies to assist with the remedial action and redevelopment of the Outer Harbor in Buffalo, New York.

Phase I, Soil Mixing
The initial phase of the project included the in-situ chemical oxidation to stabilize the nitrobenzene-impacted soil. RECON installed 155 columns using the Single Auger Mixing (SAM) technique. The 8-foot diameter columns were overlapped to ensure the entire 5,400 cubic yards of impacted soil was treated. Oxidizing agent (Potassium Permanganate) was introduced at a rate of approximately 600 pounds per column and was mixed with the impacted soil between 8.0 and 22.0 feet below ground surface for 20 minutes.

RECON used its own RH190 Delmag crawler-mounted hydraulic drill rig to advance, rotate, and withdraw the mixing tool. The drill rig has a top drive rotary head capable of transferring 190,000 foot-pounds of torque to the mixing tool. The RH190 is capable of producing a crown force of 73,000 pounds and an extraction force of 92,000 pounds. It is equipped with a cab-mounted, real-time monitoring system that allows the driller to control the soil mixing operation by monitoring the tool rotation speed, tool penetration, and agent/grout placement.

Phase 2, Jet Grouting
Phase 2 included injecting additional Potassium Permanganate to treat "hot spot" areas identified after verification sampling. RECON used our jet groutin rig to deliver the reagent because the chemically oxidized area was impassible, and the jet grouting rig provided angular drilling.

RECON's jet grouting rig includes a hydraulic drill equipped with the capability of injecting reagent. This procedure influenced a 1-foot diameter zone around the drill stem. RECON's high-pressure pump delivered reagent at a rate of 40 gpm at a pressure of over 6,500 psi. The jet grout pump delivered the reagent solution from an agitated holding tank through a hose to a swivel on top of the mixing tool shaft. The swivel allows the reagent mix to flow through the shaft and exit through ports on the mixing tool while the tool is rotating. The flow rate was modified at the pump with a flow meter to ensure placement of the prescribed reagent dose.

Phase 3, Soil Stabilization and Final Treatment
Toxicity Characteristics Leaching Procedure (TCLP) levels of nitrobenzene were lowered to a maximum of 35.4 ppm as a result of Phase 1 and 2 treatment events. Treatability studies were performed by RECON to determine the percentage of cement required to stabilize the remaining fluidized material. Additionally, it was decided to mix 4% granular activated carbon (GAC) to absorb the majority of the remaining nitrobenzene. Adding the GAC reduced the nitrobenzene levels by 98%.

After the treatability studies were presented to, and accepted by, the agencies, RECON re-mobilized the Delmag soil mixing rig to perform cement-GAC stabilization of the fluidized area as the final treatment.

 

Back to Top
WATER SUPPLY INTAKE STRUCTURE
Statesville, Alabama


This project used jet grouting to construct insitu mixed columns of soil and grout to accomplish the following tasks in support of a microtunneling operation:
  • Stopping a major leak of water and fluidized sand into the micro-tunneling jacking shaft.
  • Grouting quick soils within 25 feet of jacking shaft to create a stable drilling corridor.
  • Installing stabilized columns to underpin a footing located above the drilling corridor.
Remedial Construction Services, L.P. (RECON) installed twenty-two, 36-inch diameter columns, to depths greater than 80 feet. The unconfined compressive strength (UCS) of the grouted soil could not exceed 1000 psi in 28 days, to accommodate microtunneling through the solidified mass.

Jet Grouting is a replacement/mixing technology where a high-pressure “jet” of grout is used to erode and mix in-situ soil to create a blended mass of grout and soil with improved engineering properties. The columns were installed using RECON’s state-of-the-art equipment including an automated grout batch plant, high-pressure pump and hydraulic drill equipped with a 2-fluid Jet Grout drill string.

Difficulties presented during this project included:
  • A rapid mobilization and construction schedule.
  • Breaking and adding rods during drilling and grouting, because of the required depths.
  • The jet grout columns were drilled at varying angles, to work around the pump station foundation and structure.
Back to Top

SIMS BAYOU
Houston, Texas


Sims Bayou is a major stormwater conveyance feature that comes under the auspices of the U.S. Army Corps of Engineers (USACE). When a deep failure plane -- caused by the presence of low-strength soils combined with a seasonal upward hydraulic gradient -- developed along a stretch of the bayou’s 20-foot high embankment, the USACE selected the single-fluid jet grouting technique to stabilize the slope.

Jet grouting is a replacement mixing technology that uses a high-pressure jet of grout to erode and mix the soils in situ, creating a blended soil/grout matrix with improved engineering properties.

Jet Grouting Program
The intent of the jet-grouting program was to intercept the active failure plane and prevent further soil movement into the bayou. Deleterious material was excavated and the area was backfilled to construct a stable working platform. Jet grouting was accomplished using Remedial Construction Services, L.P. (RECON’s) state-of-the-art equipment, including an automated grout batch plant, high-pressure pump, and hydraulic drill equipped with a single-fluid jet grout drill string. RECON installed 120,30-inch diameter jet grout columns to a depth of 32 feet, creating a stabilized zone of soil approximately 100 feet long and 10 feet wide. The project was successfully completed within the 240-day schedule.

Quality Control and Quality Assurance
Prior to production work, six test columns were installed within the area of the permanent system. After being allowed to cure, all six columns were excavated and visually inspected to verify that the required column diameter could be achieved in the highly plastic Gulf Coast clays. One unconfined compressive strength (UCS) test was performed for every ten production columns to ensure that the specified minimum UCS of 250 psi in 28 days had been achieved.

Site Restoration
In addition to the jet-grouting program, RECON performed the following items of work at the site:

  • Installation of silt barriers to protect Sims Bayou during construction,
  • Installation of a cellular concrete mattress from the base of the jet-grouted section to below the water line to prevent erosion of the slope into the bayou.
  • Installation of relief wells and drainage structures, and
  • Restoration of the slope to its pre-failure cndition, including turfing and tree planting.
Back to Top
pagebottom001.gif - 2639 Bytes
JET GROUTING TECHNOLOGY OVERVIEW | GROUND MODIFICATION SPECIFICATION | GROUND IMPROVEMENT TECHNICAL ARTICES | GEOTECHNICAL CONSTRUCTION CASE HISTORIES | GROUTING CONTRACTORS INDUSTRY DIRECTORY | JET GROUTING EVENT CALENDAR | JET GROUTING JOBS | GROUND IMPROVEMENT TECHNIQUES DISCUSSION FORUMS | GEOTECHNICAL SERVICES ENGINEERS ESTIMATES | DEEP SOIL MIXING TECHNICAL ASSITANCE | CONTACT JET-GROUTING.COM | JET GROUTING HOME | SITE MAP | RETURN TO TEKTRACKER.COM




WWW.TEKTRACKER.COM | WWW.AUGERCASTPILES.COM | WWW.BIOPOLYMERTRENCH.COM | WWW.DEEPFOUNDATIONS.COM | WWW.DEEPSOILMIXING.COM | WWW.DIAPHRAGMWALL.COM | WWW.GROUNDWATERREMEDIATION.COM | WWW.JET-GROUTING.COM | WWW.PERMEABLEREACTIVEBARRIER.COM | WWW.SECANTPILE.COM | WWW.SEDIMENTCAP.COM | WWW.SHEETPILE.COM | WWW.SLUDGESTABILIZATION.COM | WWW.SLURRYWALL.COM | WWW.SOIL-MIXING.COM | WWW.SOILMODIFICATION.COM

© 2005 www.tektracker.com | Site Design by: eNet Technologies